KAPA planning - filtering work phases by time period
A
Andreas Steeb
There should be a function in deployment planning that, for example, you can filter all projects that are currently in work phase 8 by a period of time. One example of application would be that an overview can thus be quickly created for planning summer vacations as a representative for construction management.
S
Simon Winkler
... if this filter were then stored with the commissioned fees in the phase, that would be even nicer - so far, we have always made plans in Excel (including for personnel planning, etc.) as to how many projects will run next year, for example in LP 8, and how busy our BL will be.
Arne Semmler
Simon Winkler: Something of this kind is currently under development about the evaluation Office->Evaluates->Projects by period. Here you can already filter by performance date (e.g. LP8) for the past and we build certain evaluations (e.g. expected turnover) especially for the future...
S
Simon Winkler
Arne Semmler thanks for the quick response! We have already found the evaluation, it is actually about foresight - we are very excited about it and are happy to be available as testers.